Projects Under Design

Burnt Hickory road at Brownsville extension and stout parkway

This project involves intersection improvements for the intersection of Burnt Hickory Road at Brownsville Extension and Stout Parkway. Currently the intersection is a four-way stop. This is a safety project designed to help address intersection deficiencies.

The design phase began in April 2018 at a cost of $119,670. This project has a construction let date of March 2022. This project is funded by SPLOST funds, but it is a joint project with Cobb County and the project costs will be split.

sr 101 at sr 120

This project involves intersection improvements for the intersection of SR 101 at SR 120. Currently the intersection is a four-way stop. This is a safety project designed to help address intersection deficiencies.

The design phase began in January 2017 at a cost of $149,684.  Right of way acquisition is currently in progress. Construction is anticipated to begin in 2022. This project is funded by SPLOST funds, but additional State funds will be requested as both roadways on a State route.

sr 101 at goldmine road

This project involves intersection improvements for the intersection of SR 101 at Goldmine Road. This is a safety project designed to help address intersection deficiencies.

The design phase began in May 2018 at a cost of $283,509. Right of way acquisition is currently in progress.  Construction is not anticipated to begin until the year 2022. This project is funded by SPLOST funds, but additional State funding will be requested to help fully fund construction of this project.

Cedarcrest Road Corridor Improvement from Harmony Grove Church Road North to the Cobb County Line.

This project is 3.3 miles of existing roadway that consists of widening to a four lane section with a 20 foot median between Harmony Grove Church Road and the Cobb County line. The project will also include upgraded shoulders and pedestrian facilities.

A Request for Proposals (RFP) was advertised for this project in 2017. TranSystems was selected, out of five engineering firms, and awarded the preliminary engineering design services contract on December 12, 2017 in the amount of $2,582,898.18 by the Paulding County Board of Commissioners.

The project design phase began in January 2018 at a cost of $2,582,898. This is a multiyear project that is planned to begin Right of Way Authorization by April 2021 and construction planned for April 2026.

A Public Information Open House was held on January 24, 2019. The concept drawings presented at this open house are below. Coordination will be required with GDOT including assistance with funding. Funding for this project will come from SPLOST with additional funding from the State for construction costs.

Conceptual Plan

Response Letter: /DocumentCenter/View/8723/0013700_ResponseLetter_v3_April-2019

Bobo Road at Mt Tabor Church Road & Macland Road

This project involves intersection improvements at both the Mt Tabor Church Road at Bobo Road and Macland Road at Bobo Road. Roundabouts are being studied at both locations to address the current intersection deficiencies.

The design phase began in May 2018 at a cost of $341,586. Construction is not anticipated to begin until the year 2022. This project is funded by SPLOST funds.